Key Dates
13 August 2018
Section 3 commences
Section 3 of the High Street Upgrade is underway and will require the road to be closed to all traffic, between Station and Henry Streets.The closure will be in effect for 5 weeks, from 13 August – 16 September.
Night works will continue at the Station and High Street intersection, until Friday 24 August.
30 July 2018
Work starts: Station St intersection
Night works begin at the intersection of Station and High Streets. Traffic controls will be in place at this intersection between 9pm and 5am, Monday to Friday, until 24 August.16 July 2018